• Using engineer-procure-construct to achieve cost, schedule and performance objectives, LANXESS has a new, strategically located high-performance materials compounding plant in the United States.

file under: Chemicals, Design-Build, Facilities, Industrial, North America, United States

Chemicals + Design-Build

Pedal to the Plastic

Design-build delivers an innovative compounding plant

The new LANXESS high-performance materials compounding plant in Gastonia, North Carolina, USA, is the perfect platform for premium plastics. Not only does this high-tech extrusion facility strategically place LANXESS near U.S. automotive manufacturers, which make up the world’s largest high-tech plastics market, but it also serves as a model for the efficient implementation of a new manufacturing plant. Using the engineer-procure-construct (EPC) approach, CDM Smith designed and built the facility through a highly collaborative effort that accommodated unique technological and architectural constraints while delivering the project safely, on time and within budget.

 
It was critical to build this plant as quickly as possible. Design-build allowed us to meet our objectives—budget, schedule, capacity, and plant operations and reliability. —Bryan Hug, LANXESS facility manager 

Living on the Fast-Track
Central to the 20,000-metric-tons-per-year compounding plant is the 42,000-square-foot, two-story production, administration and laboratory building, which houses an advanced extrusion process train. The 9-acre site also includes a 10,000-square-foot high-density raw materials storage warehouse, loading and unloading facility, as well as large raw material and finished product silos. Providing the project’s engineering and permitting, including civil, structural, mechanical and electrical detailed design was complex enough. However, LANXESS also had a non-negotiable 9-month schedule for construction completion—driven by several public relations events scheduled around the plant’s fixed grand opening date. “It was critical to build this plant as quickly as possible,” states Bryan Hug, LANXESS facility manager. “Design-build allowed us to meet our objectives—budget, schedule, capacity, and plant operations and reliability.”

To be highly responsive and flexible, CDM Smith project engineers, constructors and the owner’s project manager met daily for the project’s first 3 weeks. And, for the next 4 months, daily team calls were held to discuss design and construction issues and scheduling. To help meet the aggressive schedule, multiple bid and procurement packages were negotiated with the city, including an initial site package that allowed construction to begin prior to final design, a steel building and envelope package for the receipt and immediate placement of LANXESS’ direct-purchased production equipment, and a final interior fit-up package. Two staggered 10-hour shifts per day, for 6 or 7 days per week, allowed trade workers to efficiently complete construction within the same space and meet the project deadline.

Building to Cost and the Unknown
To further ensure the success of LANXESS’ first U.S. design-build project, CDM Smith’s construction cost estimates allowed the client to evaluate plant construction alternatives during preliminary design. Significant and incremental changes were made to structural and underground infrastructure systems that eliminated costs while maintaining operational value. For example, an outside utility structure was moved inside nearer the extrusion train, saving piping costs.

The Gastonia project also illustrates how to build with evolving design. Since the plant was to accommodate a vendor’s plastic extrusion process, which was not completely defined until construction began, the project was too complex for traditional design-bid-build. To keep momentum, engineers adapted by designing the facility based on similar plants in China, India and Germany. Frequent meetings between the project team and the extrusion vendor communicated the process specifications as they became known, so the facility design could be modified accordingly. “Our knowledge and expertise of the process system was fully incorporated throughout design and construction, including thorough review and sign-off at every stage,” notes Hug. “This was especially evident in adjusting building features to meet the requirements of the compounding equipment train being designed and installed by a separate design-builder.”

Demonstrating the LANXESS Brand
CDM Smith provided the design and installation of landscaping, interior spaces and finishes, a high-capacity push-back racking storage system and integrated fire suppression and laboratory. Set in the Gastonia Technical Park, which attracts high-tech manufacturing, the facility had to comply with stringent architectural and landscaping requirements, including the use of concrete or pre-cast building. Realizing these structures would take too long, the project team recommended pre-engineered metal building (PEMB) to meet schedule. Aesthetically pleasing metal panels were selected that blended well with the tech park setting, while giving LANXESS a modern-looking, advanced facility that conveys the firm’s brand.

LANXESS